Overview

There are over 2,400km of sealed and unsealed roads in the Wagga Wagga Local Government Area maintained by Wagga Wagga City Council.

Maintenance is carried out to prolong the life of the road and to decrease the speed of deterioration. Repairs are prioritised based on the urgency and risk to road users.

The types of work undertaken on roads includes: resealing, grading (unsealed), kerb and gutter, flood damage restoration, road rehabilitation, asphalt works, re-sheeting and final seals.

Notification of roadworks

Letters will be sent to residents, businesses and organisations ahead of roadworks taking place in their street or neighbourhood.

VMS (Variable Mobile Signage) boards will appear one week before disruptive works start (for road closures and lane closures).

While every effort is made to inform all stakeholders of impending works, it is not always possible to notify every stakeholder of the disruptions.

Given the nature of the type of work required, the timing of roadworks constantly changes due to external factors including poor weather conditions (i.e. rain, thunderstorms), and site constraints. We thank the public for their patience in the case of delays to works being undertaken.


Current and upcoming roadworks

Below is a list of current and upcoming roadworks occurring in the Wagga Wagga Local Government Area. This listing is updated regularly, please check back for updates.


Wagga Wagga CBD

Road / StreetDescription of WorksStatus
Forsyth Street – between Baylis Street and Berry Street
Road reconstruction with full-depth asphalt with potential for additional stabilisation.
Asphalt works complete, line marking to come.
Berry Street – between Morgan St and Forsyth St

Road reconstruction with full-depth asphalt with potential for additional stabilisation.
Asphalt works complete, line marking to come.
Morgan Street – between Blake St and Tarcutta StRoad reconstruction with full-depth asphalt.Underway : 27 November to 15 December 2024
Morgan St – between Docker St and Murray StRoad reconstruction with full-depth asphalt.
Underway: 4 December to 10 December 2024

Lake Albert

Road / Street Description of WorksStatus
Kyeamba Ave - east from Vincent RdRoad rehabilitation with new sprayed seal Commenced
Vincent Road - between Brunskill Rd and Maple RdRoad rehabilitation with new sprayed seal Expected start date January 2025
Main Street - between Lake St and Ontario DrRoad rehabilitation with new sprayed seal Expected start date January 2025


Fernleigh Rd/Glenfield Rd

Road / StreetDescription of WorksStatus
Glenfield Rd/Fernleigh Rd roundabout Road reconstruction with full-depth asphalt Complete, line marking to come


Kooringal Road

Road / StreetDescription of WorksStatus
Kooringal Rd – 200m stretch south of Simkin CresRoad reconstruction with full-depth asphalt.Complete - line marking to come
Kooringal Rd - Fay Ave to
Vincent Rd
Road reconstruction with full-depth asphalt. Complete - line marking to come
Kooringal Rd – Hammond Ave to
just north of Marshalls Creek Bridge
Road reconstruction with full-depth asphalt.Complete - line marking to come


Holbrook Road

Road / Street

Description of Works

Status

Holbrook/Deakin

Road reconstruction with full-depth asphalt

Complete - line marking to come

Holbrook and
Featherwood intersection
Road reconstruction with full-depth asphaltComplete - line marking to come

Holbrook and
Clifton intersection

Road reconstruction with full-depth asphalt

Complete - line marking to come


Bourkelands

Redhill/ Berembee Road

Road reconstruction with full-depth asphalt

Complete - line marking to come



Completed works

Best St/ Forsyth St roundabout

Road reconstruction with full-depth asphalt.

Completed

Best St/ Morgan St roundabout

Road reconstruction with full-depth asphalt.

Completed

Best St/ Tompson St roundabout

Road reconstruction with full-depth asphalt.

Completed

Church St - full length

Road rehabilitation with new asphalt
wearing course.

Completed

Cross Street - full length

Road rehabilitation with new asphalt
wearing course.

Completed

Johnston St Tarcutta St
to Church St

Road rehabilitation with new asphalt
wearing course.

Completed

Travers St/ Trail St intersection

Road reconstruction with full-depth asphalt

Completed

Travers St/ Fitzmaurice St
intersection

Road reconstruction with full-depth asphalt.

Completed

Reddoc Drive

Road rehabilitation with new sprayed seal.

Complete

Arnott St - full length

Road rehabilitation with new sprayed seal.

Complete

Pinaroo Dr/Fernleigh Rd intersection

Road reconstruction with full-depth asphalt.

Complete

Boorooma St - from Farrer Rd to Avocet Dr
Road rehabilitation with new sprayed seal.Completed
Dobney AvenueRoad reconstruction with full-depth asphalt.Completed

Bakers Lane - 300m stretch south from Hammond Ave

Road rehabilitation with new sprayed seal + removal of current median.

Complete

Nesbitt St - full length

Road rehabilitation with new sprayed seal.

Complete

Norton St – full length

Road rehabilitation with new sprayed seal.

complete

Gregadoo Rd - 200m east of
Plumpton Rd to 200m east of
Plunkett Dr
Road rehabilitation with new sprayed seal.Completed

Copland St – from Kooringal Rd
to Blaxland Rd

Road rehabilitation with new sprayed seal.

Completed

Copland St – from Lake Albert Rd to Tumbarumba Branch line level crossing

Road rehabilitation with partial new sprayed seal and partial new asphalt wearing course.

Completed

Kooringal Rd – between Plumpton Rd and Lake Albert Rd

Road rehabilitation with new asphalt wearing course.

Completed

Copland St/ Kooringal Rd roundabout

Road reconstruction with full-depth asphalt.

Completed

Kooringal Rd/Lake Albert Rd roundabout

Road reconstruction with full-depth asphalt.

Completed

Ziegler Ave - Stanley St
to north of Berala St

Road rehabilitation with new sprayed seal.

Complete

Road / Street

Description of Works

Status

Main St (Lake Albert) - from Lake St
south to bridge over Crooked Creek

Road rehabilitation with new sprayed seal.

Complete

Balmoral Crescent

Road reconstruction with full-depth asphalt

Complete

Byrnes Rd – 1.3km from Trahairs
Rd heading south

Road rehabilitation with new sprayed seal.

Complete

Keajura Rd – 2.6km stretch leading
on to the Hume Highway south
of Tarcutta

Road construction to seal unsealed road.

complete

McNickle Rd – 120m stretch starting from Sturt HwyRoad rehabilitation with new sprayed seal.Completed

O’Briens Creek Rd – 1.2km

Road rehabilitation with new sprayed seal.

Complete

Oxley Bridge Rd – multiple heavy patches

Road rehabilitation with new sprayed seal.

Complete

Road / Street

Description of Works

Status

Raye Street

Road rehabilitation with new sprayed seal.

Complete

Miller Ave

Road rehabilitation with new sprayed seal.

Complete