Dunns Road report 7 December 2023

11 December 2023

Dunns Road 3.3 km sealed reconstruction - COMPLETE

The 3.3 kilometres of Dunn’s Road between the Olympic Highway and Kunzea Place is virtually complete with road sealing and line marking. The road will remain to closed to through traffic until the roundabout at the Holbrook Road intersection is complete.

Upgrade of the Olympic Highway/ Dunns Road intersection - COMPLETE

This stage of the project is now complete other than some lighting work to be completed and formal adoption by Transport for NSW.

Holbrook and Dunns Roads intersection works: UNDERWAY

This stage of the project involves the construction of a roundabout at the eastern end of Dunns Road at the intersection with Holbrook Road. Work has started with initial clearing, drainage, and associated earthwork operations. Any detours necessary during construction will not be implemented until after January 8, 2024. Construction will continue until early 2024, weather permitting. Detours will be in place.