Works progressing on Forest Hill Link construction

7 November 2025

The rail corridor section between Bakers Lane and Elizabeth Avenue has experienced a number of updates, including construction of the road base and asphalt spray seal on approximately 2.5km of the rail corridor shared path, with around 500 metres of concrete works still be completed.

On the access corridor between Mitchell Road and Bakers lane, 700 metres of concrete path has been constructed, with 200 metres remaining.

Work commenced on Elizabeth Avenue, between Mangrove Crescent and the rail corridor, in first week of November, with preparations for the road base undertaken on this section of what will be a concrete shared path.