Forest Hill Link works rolling on

9 October 2025

Works are progressing on the Forest Hill Link, with works approaching completion along the northern end of Mitchell Road.

On Kyeamba Avenue, the asphalt and concrete shared path, line markings and signage have been installed along length from Mitchell Road to just east of intersection with Vincent Road.

The next stage of works will be undertaken along an access corridor between Mitchell Rd and Bakers Lane, and along Bakers Lane, the rail corridor and Elizabeth Avenue.